Duration of the project: October, 2010 through September, 2012
Architect: Maurice Jennings Architects
General contractor: Baldwin Shell
Products: PPG Insulated glass set in channels and concealed by stone, Kawneer 1600 Skylite
Special circumstances: Many challenges setting the glass many times with stone in the way.